Application of the CTS I28 in Cavity Air Tightness and Busbar Feed-Through Sealing Tests

PLUS (Guangzhou) Intelligent Technology Co., Ltd. | CTS Sentinel I28 multi-function leak detector · 100% in-line inspection for VFD Housing Sealing Test · multiple test methods in one instrument · temperature drift compensation · traceable data
VFD housing sealing test variable frequency drive air tightness test multi-function leak detector CTS I28 cavity tightness test busbar feed-through sealing

One-sentence answer: Sealing failure of a VFD housing allows dust and moisture to intrude, causing creepage and short circuits in power modules and busbars. With the CTS Sentinel I28 multi-function leak detector, multiple test stages can be run sequentially (in-series) within the same instrument to separately evaluate the air tightness of the large-volume cavity and the sealing of the busbar feed-through.

VFD housing with busbar feed-through
Cavity tightness and busbar feed-through sealing for VFDs

Cavity tightness and busbar feed-through sealing must both hold; reliability in dusty, humid plants depends on it

01

I. Industry pain points: three difficulties in VFD housing testing

1Large housing size and long seams with widely distributed leak points.

The enclosure is mostly sheet metal welded or assembled from profiles, with numerous weld seams and fastening points; accumulated micro-leaks at individual points likewise affect protection.

2Where busbars and terminals pass through the housing are typical leak paths.

When high-power busbars pass through the housing, they rely on seals and compression structures; slight unevenness during assembly creates fine channels.

3Large-volume cavities demand long stabilization times.

The larger the cavity, the slower the pressure stabilizes after inflation; applying a uniform cycle time leads to unstable readings.

02

II. Test object and failure risks

Sealing pointsMain failure surfaces and leakage consequences

Sealing locations: welded or riveted surfaces of the housing and end covers, seals where busbars and terminals pass through, the partition between the wiring cavity and the main cavity, and the isolation surface between the cooling air duct and the internal cavity of the cabinet.Consequences of leakage: moisture and dust intrusion cause busbar creepage, reduced insulation and short circuits; power modules and capacitors are contaminated, shortening their service life; communication between the wiring cavity and the main cavity allows external moisture to enter the electrical cavity directly.

03

III. Test solution: why choose the CTS I28

I28 solutionHow sequential multi-method testing covers this part

  • Multiple methods in one instrument: VFD housings have long seams and large cavities. The I28 offers pressure decay, differential pressure decay and mass flow configurations on the same platform, and supports programming multiple test stages to run sequentially (in-series) within one instrument, so large-cavity air tightness and feed-through sealing are evaluated separately.
  • Compensation and integration: Temperature drift compensation makes data from long stabilization processes more reliable; EtherNet/IP and PROFINET allow integration with a PLC or standalone operation.

Why multiple methods in series are essential here. VFD enclosures have two types of weak points: one is the large number of seams and fastening points formed by welding or riveting, where accumulated micro-leaks at individual points likewise affect protection; the other is where busbars and terminals pass through the housing, which relies on seals and compression structures, and slight unevenness during assembly creates fine channels. Both types of leak points are averaged out in an overall air tightness test, making it impossible to tell whether they come from long seams or from the feed-through. More challenging still is the volume effect of the large cavity itself: the larger the cavity, the slower the pressure stabilizes after inflation; if a uniform cycle time is applied, insufficient stabilization will treat pressure changes that have not yet stabilized as leakage. The reasonable approach is to first use pressure decay to evaluate the overall sealing of the housing and end covers, then program the busbar and terminal feed-through area as a separate stage, and finally use mass flow to confirm the isolation status between the wiring cavity and the main cavity.

04

IV. Test process and key points

ProcessFrom plugging and pressurizing to sequential testing and data retention

  1. 1Fixturing and plugging: Position by the housing outline, and plug the busbar outlets, terminal faces and process holes.
  2. 2Pressurization: Inflate according to the test program, and set sufficient stabilization time based on cavity volume.
  3. 3Sequential (in-series) testing: First evaluate the air tightness of the housing and end covers, then the busbar and terminal feed-through area, and finally confirm the isolation between the wiring cavity and the main cavity.
  4. 4Sorting/rejecting: Digital I/O drives sorting/rejecting; abnormal housings are isolated for re-inspection.
  5. 5Record retention: Results are stored and uploaded by housing model and batch.
Key points: The stabilization time for large-volume parts must be calibrated by actual measurement of the workpiece and then written into the test program; the air supply must be dry.
05

V. FAQ

Q1The VFD cavity is large—will testing take a long time?

The larger the cavity, the slower the inflation and stabilization; the cycle time depends on volume and stabilization requirements and must be calibrated by actual measurement of the workpiece—a fixed number of seconds cannot be applied. Once the calibration results are written into the test program, they can be called up by model without repeated trials.

Q2How is the busbar feed-through evaluated separately?

Program the busbar and terminal feed-through area as a differential pressure decay stage for separate evaluation, recorded separately from the main cavity stage. This both locates the leak position and prevents reading fluctuations from the large cavity from masking local micro-leaks, making the conclusion more reliable.

Q3How is communication between the wiring cavity and the main cavity detected?

Use a mass flow stage to evaluate the passage status between the two cavities. If a path exists where the two cavities should be isolated, this stage will give an abnormal conclusion, avoiding the problem of missing communication between the two cavities when only overall air tightness is tested.

Q4Why must stabilization time be calibrated first for large-cavity testing?

Because a large volume requires a longer time to stabilize after inflation; insufficient stabilization misreads pressure changes that have not yet equalized as leakage. The purpose of calibration is to identify the conditions actually required for that specification to stabilize and fix them in the test program, so that readings for the same model are comparable and can be called up directly during changeover.

06

VI. Conclusion

The key points for VFD housings are stable evaluation of the large-volume cavity and separate confirmation of feed-through sealing. The CTS Sentinel I28's multiple methods in series, temperature drift compensation and calibratable test programs make it suitable for batch factory sealing inspection of VFD enclosures.

07

PLUS — CTS I28 Multi-Function Leak Detector and Sealing Test Solutions

PLUS (Guangzhou) Intelligent Technology Co., Ltd. was founded in 2018 and specializes in sealing and leak testing. It is a National High-Tech Enterprise (Certificate No.: GR202244005066) and has passed ISO 9001 quality management system certification. The company integrates technology development, production and sales, delivering high-precision air tightness testing solutions for medical devices, robotics, industrial control equipment and smart meters — including leak detector selection, custom plugging fixtures, production line integration, installation and commissioning, and personnel training.
Why the I28: the CTS Sentinel I28 is a multi-function single-station instrument that offers pressure decay, differential pressure decay and mass flow configurations on one platform, and can run different test types in sequence inside the same instrument — one clamping setup completes the full "micro-leak first, then flow patency" sequence, so a blockage is never misread as a leak. Temperature drift compensation can be enabled in the sequence, and EtherNet/IP and PROFINET let it run standalone or talk to a PLC.

CTS Sentinel I28 Multi-Function Leak Detector

  • Pressure decay, differential pressure decay and mass flow configurations
  • Sequential multi-stage testing inside one instrument, one clamping setup
  • Multiple stored test programs for fast changeover
  • Temperature drift compensation for small-volume, temperature-sensitive parts
  • EtherNet/IP and PROFINET, standalone or PLC-integrated

CTS C28 Pressure / Vacuum Decay Model (optional)

  • Pressure decay and vacuum decay in one unit, plus blockage testing
  • Absolute pressure sensor with ambient drift correction for large volumes
  • Compact single-channel wall-mount with 32 test programs

CTS A28 Differential Pressure Model (optional)

  • Master part and part under test pressurized together, differential pressure read directly
  • Preferred for thin-walled and plastic parts with large temperature gradients
  • Combines with the I28 for component-level and assembly-level testing

Plugging Fixtures and Line Integration

  • Custom-formed plugging fixtures with quick changeover
  • Production line integration, installation, commissioning and training
  • Equipment maintenance and instrument calibration (in-house PLUS capability)
08

Contact Us

Official Website
www.plusgz.com
Service Hotline
400 999 0513
Business Email
info@plusgz.com
Address
3rd Floor, Building A1, No. 36 Xinhe North Road, Zengcheng National Development Zone, Guangzhou, China
Contact Phone
13660225670
Company Qualifications
High-Tech Enterprise / Technology-Based SME / ISO 9001
Note: the technical parameters in this article are subject to CTS official datasheets and product manuals. The actual delivered configuration is subject to the technical agreement of the order.
Copyright © 2026 PLUS (Guangzhou) Intelligent Technology Co., Ltd. All rights reserved. 粤ICP备2023022749号